U MJESECU JANUARU 2016. GODINE NAKON PROVEDENOG POSTUPKA NABAVKE JP ELEKTROPRIVREDA BIH SARAJEVO JE SA KONZORCIJOM ŠTRABAG – KONČAR ZAKLJUČILA UGOVOR O IZGRADNJI HE VRANDUK NA RIJECI BOSNI KAPACITETE 100 GWH ENERGIJE NA GODIŠNJEM NIVOU UKUPNE VRIJEDNOSTI 112.3 MILIONA KM.
POČETAK RADOVA JE PLANIRAN ZA MJESEC APRIL 2016. GODINE, A PROIZVODNJA STRUJE OD STRANE HE VRANDUK JE PLANIRANA DA POČNE 01.11.2019. GODINE.
RAZLOZI ZA KAŠNJENJE U IZVOĐENJU RADOVA SU BILI U ČINJENICI DA NIJE OKONČANA IZRADA GLAVNOG PROJEKTA OD STRANE IZVOĐAČA RADOVA, A ELEKTROPRIVREDA JE KASNILA U IZBORU NADZORA NAD RADOVIMA.
KAMEN TEMELJAC ZA IZGRADNJU OVOG OBJEKTA POLOŽIO JE SLAVODOBITNO 08.06.2016, GODINE PRVI U BOŠNJAKA BAKIR IZETBEGOVIĆ OBEĆAVŠI PRITOM DA ĆE BOSNA I HERCEGOVINA NAPOKON POSTATI JEDNO VELIKO GRADILIŠTE.
DA TAKO NEĆE BITI, ODNOSNO DA OD OBEĆANJA PRVOG U BOŠNJAKA OSTAJE SAMO PRAZNO SLOVO NA PAPIRU POKAZAĆE NADOLAZEĆE VRIJEME KOJE ĆE SVE OVO DEMANTOVATI.
SVE AKTIVNOSTI OKO IZGRADNJE OVOG OBJEKTA ZA PROIZVODNJU ELEKTRIČNE ENERGIJE ĆE SE POKAZATI KAO NOĆNA MORA, ODNOSNO ULAZAK U POSAO PO SVAKU CIJENU ŠTO ĆE U KONAČNICI DOŽIVJETI POTPUNI KRAH, ŠTO JE BILO I ZA OČEKIVATI.
U POSAO SE U PRVOM REDU UŠLO BEZ JASNO I PRECIZNO IZRAĐENOG PROJEKTA, TAKO DA SE U PRVOM REDU MNOGO TOGA UOPĆE NIJE ZNALO.
NEKORDOINACIJA UPRAVE ELEKTROPRIVREDE, NADZORNOG ORGANA I IZVOĐAČA RADOVA JE BILA VIŠE NEGO OČIGLEDNA.
NEPOSTOJANJE ADEKVATNE DOKUMENTACIJE I PLANA RADOVA JE BILA VELIKA PREPREKA U REALIZACIJI OVOG ZNAČAJNOG PROJEKTA.
KULMINACIJA SVEGA TOGA JE OBAVIJEST IZVOĐAČA RADOVA „ŠTRABAG/KONČAR“ OD 10.04.2017. GODINE DA OBIUSTAVLJA RADOVE IZ RAZLOGA ŠTO ELEKTROPRIVREDA BIH NIJE PLATILA ZA PRIVREMENE SITUACIJE ZA PERIOD NOVEMBAR 2016 . – FEBRUAR 2017. GODINE.
NADZORNI ORGAN 12.05.2017. GODINE ODOBRAVA PRIVREMENE SITUACIJE I OMOGUĆAVA DA SE ISTE NAPLATE OD STRANE ELEKTROPRIVREDE BIH.
MEĐUTIM, PLAĆANJE PRIVREMENIH SITUACIJA OD STRANE ELEKTROPRIVREDE BIH IZVOĐAČU RADOVA „ŠTRABAG/KONČAR“ SE NIJE DESILO.
POSLIJE OVOG DOGAĐAJA UMJESTO SMIRIVANJA TENZIJA DOLAZI DO NOVOG ZAPLETA. IZVOĐAČ RADOVA „ŠTRABAG/KONČAR“ 09.07.2017. GODINE POZIVAJUĆI SE NA KLAUZULU 16.2. UGOVORA UPUĆUJE ELEKTROPRIVREDI BIH OBAVIJEST DA OBUSTAVLJA RADOVE IZ RAZLOGA ŠTO ELEKTROPRIVREDA BIH NIJE IZVRŠILA PLAĆANJE PRIVREMENIH SITUACIJA IAKO SU ISTE OD STRANE NADZORNOG ORGANA ODOBRENE 12.05.2017. GODINE.
U MEĐUVREMENU IZVOĐAČ RADOVA „ŠTRABAG/KONČAR“ UPUTIO JE 10.04.2017. GODINE ELEKTROPRIVREDI PREZENTACIJU SA PROBLEMIMA NA KOJE JE NAIŠAO TOKOM IZVOĐENJA RADOVA, KAKO SLIJEDI:
- POTREBNA SU DODATNA SREDSTVA ZA IZVOĐENJE RADOVA IZ RAZLOGA ŠTO ODREĐENI RADOVI U IDEJNOM PROJEKTU NISU DOBRO PREDVIĐENI, ODNOSNO POSTOJE ODREĐENE NEUSKLAĐENOSTI SA TENDERSKOM DOKUMENTACIJOM ZBOG ČEGA SU POTREBNA DODATNA SREDSTVA ZA IZGRADNJU ELEKTRANE I DODATNI PERIOD ZA IZVO
ĐENJE RADOVA – DUŽINA SLAPIŠTA BRANE, CESTA ZENICA VRANDUK JE DUŽINE 5,1 KM, A NE 4,1 KM I GLAVNA STROJARA NIJE DOBRO LOCIRANA.
- ZA DODATNE RADOVE JE POTREBNO DODATNIH 13 MILIONA EURA.
- BILO JE TU JOŠ NEKOLIKO PRIMJEDBI OD STRANE IZVOĐAČA RADOVA, ALI OVE SU NAJBITNIJE.
TAKOĐE, IZVOĐAČ RADOVA JE ISTO PREDLOŽIO DA SE RAZGOVARA, TE DA SE PRONAĐE KOMPROMISNO RJEŠENJE, KAKO BI SE RADOVI MOGLI NASTAVITI.
NAKON TOGA, IZVOĐAČ RADOVA JE POTPUNO SUSPENDOVAO RADOVE I TRAŽIO DODATNA SREDSTVA OD 13, 7 MILIONA EURA, ALI TO NIJE TRAŽIO U ZVANIČNOJ PROCEDURI.
ELEKTROPRIVREDA BIH JE ZAHTJEVE IZVOĐAČA RADOVA OCIJENILA KAO NEOPRAVDANE, ODNOSNO ISTE NIJE PRIHVATILA.
U DALJEM TOKU, IZVOĐAČ RADOVA NIJE KOMPLETIRAO DOKUMENTACIJU ZA PLAĆANJE PRIVREMENE SITUACIJE, VEĆ JE NAPUSTIO UGOVOR, ODNOSNO 12.06.2017. GODINE JE NAJAVI0 RASKID UGOVORA.
KAKO BI OSIGURALA BANKOVNU GARANCIJU ZA IZVRŠENJE RADOVA ELEKTROPRIVREDA BIH 12.06.2017. GODINE UPUĆUJE IZVOĐAČU RADOVA „ŠTRABAG/KONČAR“ OBAVIJEST O RASKIDU UGOVORA ZBOG NEIZVRŠAVANJA OBAVEZA PREMA UGOVORU.
ISTO TAKO, ELEKTROPRIVREDA BIH JE AKTIVIRALA BANKOVNU GARANCIJU ZA DOBRO IZVRŠENJE RADOVA OD 5,7 MILIONA EURA.. POKRENUT JE POSTUPAK ZA NAPLATU GARANCIJE PRED SUDOM U BEČU.
U MEĐUVREMENU ŠTRABAG POKREĆE ARBITRAŽNI POSTUPAK PRED SUDOM U PARIZU.
NAKON PRVE RASPRAVE, POSTUPAK JE MIROVAO ZBOG POKRENUTE AKTINOSTI DA SE UMJESTO ŠTRABAGA U POSAO UVEDE EUROASFALT ZA ŠTA JE BILA POTREBNA SAGLASNOST EVROPSKE INVESTICIONE BANKE.
NAKON ODRŽANIH PREGOVORA U ZAGREBU JE 31.10.2017. GODINE POTPISAN SPORAZUM PO KOJEM ŠTRABAG DAJE SAGLASNOST DA SE UVEDE ZAMJENSKI IZVOĐAČ RADOVA UZ ISPLATU ELEKTROPRIVREDI NAKNADE OD 100.000.00 EURA.
DOGOVORENO JE DA POSTUPAK PRED SUDOM U BEČU MIRUJE, KAO I ARBITRAŽNI POSTUPAK U PARIZU.
DANA, 04.07.2018. GODINE POTPISAN JE SPORAZUM O NASTAVKU REALIZACIJE PROJEKTA IZGRADNJE HE VRANDUK SA IZVOĐAČIMA EUROASFALT/KONČAR.
DA BI SE SE OVE AKTIVNOSTI MOGLE PROVESTI EIBRD I EIB SU TREBALE DATI SVOJU SAGLASNOST.
EIBRD DAJE 29.05.2018. GODINE SAGLASNOST ZA NASTAVAK RADOVA, ALI EIB ISTU 05.12.2018. GODINE NE DAJE OBRAZLAŽUĆI DA SE IZVOĐAČ RADOVA NE MOŽE ZAMIJENITI DIREKTNIM SPORAZUMOM.
NASTAVLJAJU SE POSTUPAK PRED SUDOM U BEČU I ARBITRAŽA U PARIZU.
SUD U BEČU PRESUĐUJE DA ŠTRABAG PLATI BANKOVNU GARANCIJU OD 5,7 MILIONA EURA.
ŠTO SE TIČE ARBITRAŽNOG POSTUPKA ŠTRABAG JE ISTAKAO TUŽBENI ZAHTJEV PREMA ELEKTROPRIVREDI U IZNOSU OD 20.07 MILIONA EURA, A ELEKTROPRIVREDA BIH PREMA ŠTRABAGU U IZNOSU OD 39,1 MILION EURA.
ARBITRAŽNI POSTUPAK JE TRAJAO U PERIODU 19.04. – 28.04.2021. GODINE, A SAMA PRESUDA JE DONESENA 31.12.2021. GODINE. PO OVOJ PRESUDI ELEKTROPRIVREDA JE DUŽNA NA IME RAZNIH NAKNADA ISPLATITI ŠTRABAGU IZNOS OD 16,7 MILIONA EURA.
U MEĐUVREMENU JE OVAJ IZNOS UVEĆAN NA 20 MILIONA EURA.
ZBOG NEPROMIŠLJENIH I LOŠIH POSLOVNIH POLTIKA I ODLUKA KADROVA SDA KOJI SU UPRAVLJALI NAJVAŽNIJIM RESURSOM U BOSNI I HERCEGOVINI ELEKTROPRIVREDOM BIH DD SARAJEVO REZULTAT NAPRIJED NAPISANE TRAGEDIJE NAŠEG DRUŠTVA JE SLIJEDEĆI:
- NIJE IZGRAĐENA HE VRANDUK KOJA BI GODIŠNJE PROIZVODILA 100 GWH ELEKTRIČNE ENERGIJE I DONOSILA PRIHOD OD 7,2 MILIONA EURA NA GODIŠNJEM NIVOU ŠTO DO DANAŠNJEG DANA IZNOSI 36 MILIONA EURA
- IZVOĐAČU RADOVA ŠTRABAGU TREBA PLATITI NAKNADU U IZNOSU OD 20 MILIONA EURA.
- SA DANAŠNJIM DANOM TO DIREKTNO I INDIREKTNO IZNOSI 56 MILIONA EURA ILI 110 MILIONA KM. IMA LI ODGOVORNIH I DOKLE ĆE SE NA OVAKAV NAČIN KRČMITI NOVAC GRAĐANA BOSNE I HERCEGOVINE, A U PRVOM REDU BOŠNJAKA.